Velocitel requests replacement of the existing tower at Wolf Mt., which is failing. The new tower will be the same height at the existing tower and in the same location. Existing footings would be replaced. Work would be in already disturbed ground.
Location
Wolf Mountain
Project timeline
1
Scoping Start
12/17/2012
2
Comment Period
12/17/2012
3
Decision
07/2013 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| AT&T/Cingular Wireless Wolf Mt. Tower Replacement Project | Decision Signed Date: 07/01/2013 Legal Notice Date: 07/05/2013 |
| Forests | Willamette National Forest |
| Districts | Middle Fork - Inactive Ranger District |
| Legal Land Description | T22S, R5E, SW 1/4 of Section 33 |