Decision Memo Completed

House Rock Bridge Replacement

Willamette National Forest Linn, Oregon Detroit Ranger District

The trail foot bridge at House Rock campground will be replaced with a pre-engineered steel bridge. Concrete abuttments would be required on either side of the South Santiam River.

Location

South Santiam Watershed

Project timeline

1
Scoping Start
01/11/2013
2
Comment Period
03/25/2013
3
Decision
06/2013 (Estimated)
4
Implementation
08/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityTrail Management
House Rock Bridge ReplacementDecision Signed Date: 06/10/2013 Legal Notice Date: 06/17/2013
ForestsWillamette National Forest
DistrictsSweet Home Ranger District
Legal Land DescriptionT13S, R5E, Section 32