Resource damage will be minimized and restored at the dispersed campsites by providing a riparian buffer, planting native vegetation, subsoiling compacted soils, deterring campsite area growth and educational signage.
Location
The project will take place along Fall Creek from Forest Service boundary near Dolly Varden campground to confluence with Buzzard Creek and major tributaries including Portland Creek and Hehe Creeks.
Project timeline
1
Scoping Start
11/26/2013
2
Decision
01/2014 (Estimated)
3
Implementation
06/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt.; Noxious Weed Treatments; Watershed Improvements |
| Respect the River Project: Fall Creek | Decision Signed Date: 01/01/2014 |
| Forests | Willamette National Forest |
| Districts | Middle Fork - Inactive Ranger District |