A Supplemental Environmental Assessment will be prepared to disclose effects of harvesting timber on about 33 acres already under contract and to respond to analysis deficiencies identified by the 2011 U.S. District Court decision.
Location
About 13 miles NE of Blue River, OR, adjacent to FS Road 1517.
Project timeline
1
Scoping Start
02/11/2013
2
Comment Period
03/17/2014
3
Objection Period Start
05/19/2014
4
Decision
07/2014 (Estimated)
5
Implementation
09/2014 (Estimated)
NEPA / regulatory detail
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Maintenance; Timber Sales (Green) |
| Forests | Willamette National Forest |
| Districts | McKenzie River Ranger District |
| Legal Land Description | T14S, R5E, Sections 34 and 35, W.M. |