The project will lessen impacts to federally listed fish habitat by decreasing sediment inputs, increasing the shade component and reducing the chance for petroleum products from vehicles entering the water by rehabilitating two dispersed campsites.
Location
T9S, R6E Sec 16 &21, Humbug Creek Watershed, 4697 road system
Project timeline
1
Scoping Start
04/24/2014
2
Decision
09/2014 (Estimated)
3
Implementation
10/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt.; Watershed Improvements |
| Humbug Dispersed Campsite Project | Decision Signed Date: 09/18/2014 |
| Forests | Willamette National Forest |
| Districts | Detroit Ranger District |
| Legal Land Description | T9S, R6E Sec 16 &21 |