This project proposes that testing would entail clearing & leveling two 40 ft by 10 ft work pads to set up the drilling equipment at each proposed structure location. This project is to determine foundation depth for future tower replacement.
Location
La Duke Road
Project timeline
1
Scoping Start
07/30/2014
2
Decision
08/2014 (Estimated)
3
Implementation
09/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Hills Creek-Lookout Point Geotechnical Drilling Project | Decision Signed Date: 08/13/2014 |
| Forests | Willamette National Forest |
| Districts | Middle Fork - Inactive Ranger District |
| Legal Land Description | T21S,R3E, Section 21 and 22 |