The District proposes to reconstruct or relocate boat launches at Frissell, Paradise, and Bruchart Launch Sites
Location
Frissell, Paradise, and Bruchart Boat Launches along the McKenzie River
Project timeline
1
Scoping Start
01/29/2003
2
Comment Period
02/26/2007
3
Decision
06/2007 (Estimated)
4
Implementation
07/2008 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Facility Improvements/Construction |
| Upper McKenzie Boat Launch Projects | Decision Signed Date: 06/14/2007 Legal Notice Date: 06/20/2007 |
| Forests | Willamette National Forest |
| Districts | McKenzie River Ranger District |
| Legal Land Description | T.16S, R.6E, Sec. 1; T.16S, R.6E, Sec. 9; T.16S, R.5E, Sec. 19; W.M |