This project will repair a section of the Bingham Fire dozer line by removing up to 30 trees of the pushed and pulled from the site to be used in fish restoration projects. Remaining pushed/pulled trees will be scattered to mimic surrounding stand.
Location
The legal location is T11S, R7 1/2E, Section 27.
Project timeline
1
Scoping Start
02/05/2015
2
Decision
07/2015 (Estimated)
3
Implementation
08/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (11), 36 Cfr 220.6(E)(11) |
| Special Authority | Not Applicable / Other; National Fire Plan - Healthy Forests Initiative Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements; Watershed Improvements |
| Decision Memo for the Bingham Fire Dozer Line Rehabilitation Project | Decision Signed Date: 07/20/2015 |
| Forests | Willamette National Forest |
| Districts | Detroit Ranger District |
| Legal Land Description | Not Applicable |