Two disconnected segments of Lawler Trail (3473) exist currently. The proposed segment will connect the currently orphaned trail segments only traveling on spur 5840-535 for 200' This will create a safer and more desirable trail user experience.
Location
Approximately, one mile south of the Hampton boat launch along Highway 58.
Project timeline
1
Scoping Start
09/29/2015
2
Decision
05/2016 (Estimated)
3
Implementation
06/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Lawler Connection | Decision Signed Date: 05/19/2016 |
| Forests | Willamette National Forest |
| Districts | Middle Fork - Inactive Ranger District |
| Legal Land Description | T20S, R2E, west half of section 29 |