Environmental Assessment Completed

Dry Beard

Willamette National Forest Linn, Oregon Detroit Ranger District

Project will commercially thin approximately 1350 acres of second growth forest in the Headwaters North Santiam Watershed. Road storage, road decommissioning and bridge replacement or repair is included in the project.

Location

This project is located south of the North Santiam River, east of Detroit Lake and north of FS Road 10 in the Headwaters North Santiam Watershed.

Project timeline

1
Scoping Start
06/20/2018
2
Comment Period
08/26/2019
3
Objection Period Start
01/21/2020
4
Decision
03/2020 (Estimated)
5
Implementation
05/2020 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityTravel Management; Timber Sales (Green)
Dry BeardDecision Signed Date: 03/16/2020
ForestsWillamette National Forest
DistrictsDetroit Ranger District
Legal Land DescriptionNot Applicable
Road managementForest products