There is a need to build two segments of trail that would get trail users off the road system and back onto the trail system. These two connections will connect Clover Patch to the Clover Patch Tie and Alpine Trail.
Location
Approximately, 5 miles northwest of Oakridge.
Project timeline
1
Scoping Start
05/09/2018
2
Decision
04/2019 (Estimated)
3
Implementation
05/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Clover Patch Connection | Decision Signed Date: 04/01/2019 |
| Forests | Willamette National Forest |
| Districts | Middle Fork - Inactive Ranger District |
| Legal Land Description | T20S, R2E, Sec 23 |