The 80 foot single stringer bridge was cut down in 2017 due to significant decay and heavy scour. A better location with natural bedrock banks is found 250 feet upstream. The trail would be rerouted to this location and the old section abandoned.
Location
Approximately 17 miles south of Oakridge, OR.
Project timeline
1
Scoping Start
05/24/2019
2
Decision
02/2021 (Estimated)
3
Implementation
04/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Indian Creek Bridge and Trail Reroute Decision Memo | Decision Signed Date: 02/24/2021 |
| Forests | Willamette National Forest |
| Districts | Middle Fork Ranger District |
| Legal Land Description | T24S, R3E, S4 SE |