Three miles of new trail (up to 48" wide and surfaced with pea gravel or wood chips) are proposed along with a 1/4 mile connector trail to the 5852 road and a few very short connector trails to make the trail system more useful and easy to follow.
Location
T21S, R3E, Sections 21, 22
Project timeline
1
Scoping Start
04/07/2021
2
Decision
07/2021 (Estimated)
3
Implementation
09/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Greenwaters Trail Expansion | Decision Signed Date: 07/29/2021 |
| Forests | Willamette National Forest |
| Districts | Middle Fork Ranger District |
| Legal Land Description | Not Applicable |