The District is proposing reconstructing 8 miles of NFSR 1506. Road work may include culvert replacement, fill slope repair and stabilization, roadway surface replacement, drainage repair and incidental tree removal associated with repair sites.
Location
NFSR 1506 Lookout Creek, MP 7.0 (Lookout Creek TH West) to MP 15.0 (Jct. with Road 1506630)
Project timeline
1
Scoping Start
04/12/2022
2
Decision
03/2023 (Estimated)
3
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| 1506 road reconstruction | Decision Signed Date: 03/13/2023 |
| Forests | Willamette National Forest |
| Districts | McKenzie River Ranger District |
| Legal Land Description | Not Applicable |