Decision Memo Completed

EWEB Carmen Campus improvements

Willamette National Forest Lane, Oregon Willamette National Forest All Units

EWEB is proposing to install two new manufactured homes, one site built garage, associated wastewater drain fields, and underground utilities. Additionally we plan to remove an existing building and replace it with an larger one.

Location

Location is at the EWEB Carmen-Smith Hydroelectric Project Carmen Campus

Project timeline

1
Scoping Start
05/18/2023
2
Decision
07/2023 (Estimated)
3
Implementation
09/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Hydropower; Facility Maintenance
EWEB Carmen Campus improvementsDecision Signed Date: 07/17/2023
ForestsWillamette National Forest
DistrictsMcKenzie River Ranger District
Legal Land DescriptionNot Applicable
Special use management