This electric line would provide existing customers with a more reliable power source and provide a sufficient power source for the expanding residential use in this area.
Location
Union County, Georgia
Project timeline
1
Scoping Start
06/23/2010
2
Comment Period
07/20/2010
3
Decision
08/2010 (Estimated)
4
Implementation
07/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Blue Ridge Mtn. EMC Overhead Powerline along US 19/129 at GA 180 | Decision Signed Date: 08/06/2010 |
| Forests | Chattahoochee-Oconee National Forests |
| Districts | Blueridge Ranger District |
| Legal Land Description | Not Applicable |