Environmental Assessment Completed

Sumac Creek Watershed Project

Chattahoochee-Oconee National Forest Murray, Georgia Conasauga Ranger District

The conditions in the Sumac Creek Project Area indicate a need to: restore and maintain shortleaf pine and xeric oak woodland communities; maintain oak communities; improve forest health; and increase structural diversity.

Location

Murray County, Georgia

Project timeline

1
Scoping Start
09/02/2011
2
Comment Period
10/07/2011
3
Decision
09/2013 (Estimated)
4
Implementation
03/2014 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityWatershed Improvements
Sumac Creek Watershed ProjectDecision Signed Date: 09/11/2013
ForestsChattahoochee-Oconee National Forests
DistrictsConasauga Ranger District
Legal Land DescriptionNot Applicable
Watershed management