Windstream’s permit request consists of installing a new overhead cable within an existing powerline right-of-way from Hwy 100 (Lickskillet Road) to the state-owned fire tower at High Point.
Location
Chattooga County, Georgia
Project timeline
1
Scoping Start
07/12/2012
2
Comment Period
08/13/2012
3
Decision
09/2012 (Estimated)
4
Implementation
12/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Windstream Communcations Fiber-Optic Cable Project-SUP | Decision Signed Date: 09/12/2012 |
| Forests | Chattahoochee-Oconee National Forests |
| Districts | Conasauga Ranger District |
| Legal Land Description | Not Applicable |