The purpose of this project is to replace two culverts on Tumbling Creek Road with open bottom “arch” type culverts. Both above and below the culverts, the streambed would be restored to its natural condition.
Location
Fannin County, GA
Project timeline
1
Scoping Start
02/05/2013
2
Comment Period
03/01/2013
3
Decision
08/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Improvements/Construction; Watershed Improvements |
| Tumbling Creek Aquatic Organism Passage Project | Decision Signed Date: 08/07/2013 |
| Forests | Chattahoochee-Oconee National Forests |
| Districts | Conasauga Ranger District |
| Legal Land Description | Not Applicable |