Upper West Armuchee Creek Watershed Project
Location
Walker and Whitfield Counties, Georgia
Project timeline
1
Scoping Start
08/05/2014
2
Comment Period
09/05/2014
3
Objection Period Start
08/31/2015
4
Decision
01/2016 (Estimated)
5
Implementation
04/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Watershed Improvements |
| Upper West Armuchee Creek Watershed Project. | Decision Signed Date: 01/13/2016 |
| Forests | Chattahoochee-Oconee National Forests |
| Districts | Conasauga Ranger District |
| Legal Land Description | Not Applicable |