The project is located in the Blue Ridge Ranger District.
Location
The project is located in Fannin county.
Project timeline
1
Scoping Start
09/25/2018
2
Decision
10/2018 (Estimated)
3
Implementation
01/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Fish Hook Point Dock Modifications | Decision Signed Date: 10/19/2018 |
| Forests | Chattahoochee-Oconee National Forests |
| Districts | Blueridge Ranger District |
| Legal Land Description | Not Applicable |