Decision Memo Completed

Installation of Fiber Optic Cable (SUP)

Chattahoochee-Oconee National Forest Union, Georgia Blueridge Ranger District

SUP to Blue Ridge Mountain Electric Membership to install a fiber optic cable on existing pole lines within an approved right of way easement on National Forest System lands.

Location

The project is located in the Blue Ridge Ranger District.

Project timeline

1
Scoping Start
10/09/2018
2
Decision
11/2018 (Estimated)
3
Implementation
11/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Installation of Fiber Optic Cable (SUP)Decision Signed Date: 11/09/2018
ForestsChattahoochee-Oconee National Forests
DistrictsBlueridge Ranger District
Legal Land DescriptionNot Applicable
Special use management