Fannin County Water Authority has submitted a request to install a water line across National Forest System lands to supply potable water to residents living at the end of Lake Cove Road.
Location
Fannin County Water Authority has submitted a request to install a water line across National Forest System lands to supply potable water to residents living at the end of Lake Cove Road.
Project timeline
1
Scoping Start
03/04/2019
2
Decision
04/2019 (Estimated)
3
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Fannin Counter Water Authority | Decision Signed Date: 04/09/2019 |
| Forests | Chattahoochee-Oconee National Forests |
| Districts | Blueridge Ranger District |
| Legal Land Description | Not Applicable |