Decision Memo Completed

Special Use Permit (SUP) for a water transmission line (Morgantown)-BRRD

Chattahoochee-Oconee National Forest Union, Georgia Blueridge Ranger District

It is a special use permit for a water transmission pipeline (<12 in diameter) on national forest land. The applicant will maintain a 4,500 feet by 2 feet wide pipeline.

Location

The SUP is located at Tract BRR-7, LL 235 &269, LL273/274, District 8 sec 2, Adra Rd & Garren Cove Rd, Fannin County, GA.

Project timeline

1
Scoping Start
11/05/2018
2
Decision
02/2019 (Estimated)
3
Implementation
03/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Area Management
Special Use Permit (SUP) for a water transmission line (Morgantown)-BRRDDecision Signed Date: 02/07/2019
ForestsChattahoochee-Oconee National Forests
DistrictsBlueridge Ranger District
Legal Land DescriptionNot Applicable
Special use management