To authorize the transfer a boat dock permit.
Location
The project is located in the Blue Ridge Ranger District.
Project timeline
1
Scoping Start
12/23/2019
2
Decision
01/2020 (Estimated)
3
Implementation
02/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Authorization Of A Permit Transfer Of A Boat Dock | Decision Signed Date: 01/24/2020 |
| Forests | Chattahoochee-Oconee National Forests |
| Districts | Blueridge Ranger District |
| Legal Land Description | Not Applicable |