The conditions in the Upper Warwoman Project Area indicate a need to restore and maintain shortleaf pine/table mountain pine/pitch pine and Dry Mesic Oak woodland communities, maintain and regenerate oak and oak-pine forests, and improve W/L habitat
Location
Rabun County, GA
Project timeline
1
Scoping Start
01/07/2013
2
Comment Period
01/28/2013
3
Objection Period Start
06/18/2015
4
Decision
10/2015 (Estimated)
5
Implementation
02/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements |
| Upper Warwoman Vegetation Management. | Decision Signed Date: 10/31/2015 |
| Forests | Chattahoochee-Oconee National Forests |
| Districts | Chattooga River Ranger District |
| Legal Land Description | Not Applicable |