Decision Memo Completed

Volunteer Electric Cooperative

Cherokee National Forest Polk, Tennessee Tellico Ranger District

Amend existing special use permit to add a 7.2 KV buried electric line at Lake Ocoee Inn. The ROW is 260 feet in length and 10 feet wide.

Location

Lake Ocoee Inn Marina Boat Slip C

Project timeline

1
Scoping Start
10/18/2007
2
Decision
02/2008 (Estimated)
3
Implementation
04/2008 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Lake Ocoee Marina PowerlineDecision Signed Date: 02/08/2008
ForestsCherokee National Forest
DistrictsOcoee - Hiwassee Ranger District
Legal Land DescriptionT1S, R3E, Section 13
Special use management