Project timeline

1
Scoping Start
03/25/2010
2
Comment Period
06/02/2013
3
Decision
09/2013 (Estimated)
4
Implementation
10/2014 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Green)
TellicoDecision Signed Date: 09/25/2013
ForestsCherokee National Forest
DistrictsTellico Ranger District
Vegetation management (other than forest products)Fuels managementSpecial use managementForest productsWatershed managementWildlife, fish, rare plantsRoad management