Place approximately 1700 ft of fiber optic cable in a 30" X 12" trench adjacent to Benton Springs Road.
Location
Benton Springs Road
Project timeline
1
Scoping Start
11/20/2013
2
Comment Period
11/26/2013
3
Decision
01/2014 (Estimated)
4
Implementation
02/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| ATT Fiber Optic Cable | Decision Signed Date: 01/22/2014 Legal Notice Date: 02/05/2014 |