Project timeline
1
Scoping Start
06/26/2015
2
Decision
11/2015 (Estimated)
3
Implementation
11/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Outfitting and Guiding Fishing permits on the Hiwassee River | Decision Signed Date: 11/13/2015 |
| Forests | Cherokee National Forest |
| Districts | Ocoee - Hiwassee Ranger District |
| Legal Land Description | Not Applicable |