Create early successional habitat, improve forest health and vigor, promote mast-producing species, prescribed burning, wildlife habitat improvements, and maintain, decommission, and authorize roads.
Location
The Meadow Creek analysis area is located in southeastern Cocke and southwestern Greene counties, TN.
Project timeline
1
Scoping Start
03/03/2017
2
Comment Period
10/12/2018
3
Objection Period Start
12/04/2018
4
Decision
04/2019 (Estimated)
5
Implementation
05/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Timber Sales (Green) |
| Meadow Creek Environmental Assessment | Decision Signed Date: 04/18/2019 |
| Forests | Cherokee National Forest |
| Districts | Unaka Ranger District |
| Legal Land Description | Not Applicable |