Decision Memo Completed

North Zone Pond Management Project

Cherokee National Forest Carter; Cocke; Greene; Johnson; Sullivan; Unicoi, Tennessee Unaka Ranger District

This project focuses on maintaining and improving ponds and waterholes across the North Zone of the Cherokee National Forest on a regular basis.

Location

North Zone Cherokee National Forest

Project timeline

1
Scoping Start
04/06/2018
2
Decision
07/2018 (Estimated)
3
Implementation
08/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements
North Zone Pond Management ProjectDecision Signed Date: 07/03/2018
ForestsCherokee National Forest
DistrictsUnaka Ranger District; Watauga Ranger District
Legal Land DescriptionNot Applicable
Wildlife, fish, rare plants