TWRA requested permission to construct a handicapped accessible fishing pier The proposed structure will consist of a wooden walkway that would end in a wooden fishing pier that will be attached to concrete piers located on bedrock on the river.
Location
Pheasant Field Rearing Pools on the Tellico River
Project timeline
1
Scoping Start
06/11/2018
2
Decision
08/2018 (Estimated)
3
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt. |
| Moment of Freedom | Decision Signed Date: 08/06/2018 |
| Forests | Cherokee National Forest |
| Districts | Tellico Ranger District |
| Legal Land Description | Not Applicable |