Decision Memo Completed

AT&T Mobility Communication Site

Cherokee National Forest Polk, Tennessee Ocoee - Hiwassee Ranger District

ATT proposes to install an 8%u2019x8%u2019 equipment cabinet on an existing concrete foundation, 20kw AC generator, H-Frame with meter and disconnect, and underground copper grounding wire and antenna installation on an existing tower structure.

Location

Sheep Top Communication Site

Project timeline

1
Scoping Start
08/28/2019
2
Decision
12/2019 (Estimated)
3
Implementation
12/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
AT&T Mobility Communication Site ProjectDecision Signed Date: 12/13/2019
ForestsCherokee National Forest
DistrictsOcoee - Hiwassee Ranger District
Legal Land DescriptionNot Applicable
Special use management