ATT proposes to install an 8%u2019x8%u2019 equipment cabinet on an existing concrete foundation, 20kw AC generator, H-Frame with meter and disconnect, and underground copper grounding wire and antenna installation on an existing tower structure.
Location
Sheep Top Communication Site
Project timeline
1
Scoping Start
08/28/2019
2
Decision
12/2019 (Estimated)
3
Implementation
12/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| AT&T Mobility Communication Site Project | Decision Signed Date: 12/13/2019 |
| Forests | Cherokee National Forest |
| Districts | Ocoee - Hiwassee Ranger District |
| Legal Land Description | Not Applicable |