This project proposes relocation of approximately 0.45 miles of the Appalachian Trail, decommissioning the old trail and re-blazing the new section of trial and installation of two gates.
Location
Appalachian Trail - near U.S 321
Project timeline
1
Scoping Start
02/07/2020
2
Decision
04/2020 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| A.T. Relo at Atwood Property Project | Decision Signed Date: 04/08/2020 |
| Forests | Cherokee National Forest |
| Districts | Watauga Ranger District |
| Legal Land Description | Not Applicable |