Decision Memo Completed

FLEC Oosterneck Road Project

Cherokee National Forest Monroe, Tennessee Tellico Ranger District

The project would install approximately 1,840 feet of three phase distribution powerline with approximately 10 new power poles and remove approximately 640 feet of electric line near Oosterneck Road.

Location

The project is located approximately 4 miles east of Tellico Plains, TN.

Project timeline

1
Scoping Start
04/06/2021
2
Decision
05/2021 (Estimated)
3
Implementation
06/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
FLEC Oosterneck Road ProjectDecision Signed Date: 05/10/2021
ForestsCherokee National Forest
DistrictsTellico Ranger District
Legal Land DescriptionNot Applicable
Special use management