The bridge would be replaced with a structure similar to the existing bridge. The existing bridge would be removed from the site and disposed of at a suitable location off of the forest. The new bridge would be constructed in the disturbed area.
Location
The project is located on Tellico River Road approximately 20 miles east of Tellico Plains, TN.
Project timeline
1
Scoping Start
02/11/2025
2
Decision
04/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Tellico Hatchery Bridge Replacement Project | Decision Signed Date: 04/02/2025 |
| Forests | Cherokee National Forest |
| Districts | Tellico Ranger District |
| Legal Land Description | Not Applicable |