Erosion and ATV/ORH damage rehabilitation on FS-160 near Gray Creek.
Location
FS-160 and Gray Creek Watershed
Project timeline
1
Scoping Start
04/25/2012
2
Comment Period
07/04/2012
3
Decision
08/2012 (Estimated)
4
Implementation
10/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Watershed Improvements |
| FS-160 and Gray Creek Watershed Restoration Project | Decision Signed Date: 08/14/2012 Legal Notice Date: 08/16/2012 |
| Forests | Kisatchie National Forest |
| Districts | Catahoula Ranger District |
| Legal Land Description | T6 N, R2 W |