New 20 KW line from a private tract in Section 26 T11N-R5W - along the Coldwater Rd, south along Lakeshore Dr to Lyles Camp and north along Lakeshore Dr. to Keyhole Rd. This project would more evenly distribute power needs to an overburdened system.
Location
Along Coldwater, Lakeshore Dr., Keyhole and Lylse Camp Rds, in Winn Parish, LA
Project timeline
1
Scoping Start
11/07/2012
2
Comment Period
11/07/2012
3
Decision
10/2013 (Estimated)
4
Implementation
11/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Entergy Amendment #37 Saline Reliability Project | Decision Signed Date: 10/18/2013 |
| Forests | Kisatchie National Forest |
| Districts | Winn Ranger District |
| Legal Land Description | Sec. 22, 26, 27 and 28 of T11N-R05W |