The Forest Service proposes to grant an SUP to AT&T to place a buried fiber optic cable along the north and south Right-of-Way of LA Hwy 8 beginning approximately 2,050 feet west of Haw Creek for approximately 1.2 mile
Location
LA Hwy 8
Project timeline
1
Scoping Start
04/03/2019
2
Decision
07/2019 (Estimated)
3
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| AT&T Ivy Fiber Optic Permit | Decision Signed Date: 07/18/2019 |
| Forests | Kisatchie National Forest |
| Districts | Catahoula Ranger District |
| Legal Land Description | Not Applicable |