The project area is approximately 6,931 acres which includes activities of thinning, clearcutting, site preparing, planting of yellow pine, releasing seedlings, mechanical fuel reduction, herbicide application, RCW cavity installation, etc.
Location
Compartments 82, 83, 84,85,90, 91, 93,94, 95, 96, 97, 100, 103
Project timeline
1
Scoping Start
01/21/2020
2
Comment Period
09/25/2020
3
Objection Period Start
11/18/2020
4
Decision
12/2020 (Estimated)
5
Implementation
01/2021 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments; Travel Management; Timber Sales (Green) |
| South Gray Creek Ecosystem Management Project | Decision Signed Date: 12/18/2020 |
| Forests | Kisatchie National Forest |
| Districts | Catahoula Ranger District |
| Legal Land Description | Not Applicable |