At&t proposes to place approx 3,507 feet of aerial fiber optic cable on Kisatchie National Forest land. This cable will be placed in the air on existing Cleco power poles.
Location
LA Hwy 8
Project timeline
1
Scoping Start
10/05/2020
2
Decision
11/2020 (Estimated)
3
Implementation
02/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| AT&T Hwy 8 Amendment 19 | Decision Signed Date: 11/02/2020 |
| Forests | Kisatchie National Forest |
| Districts | Catahoula Ranger District |
| Legal Land Description | Not Applicable |