Opening of eight new gravel pits on the Homochitto National Forest to provide for road construction and maintenance needs.
Location
Various locations across the Homochitto National Forest
Project timeline
1
Scoping Start
09/04/2011
2
Comment Period
06/2013 (Estimated)
3
Decision
07/2013 (Estimated)
4
Implementation
08/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Land Use Adjustments; Minerals Or Geology Plans Of Operations; Road Improvements/Construction; Timber Sales (Green) |
| Forests | National Forests In Mississippi |
| Districts | Homochitto Ranger District |
| Legal Land Description | T3N,R2E, Sec. 3,4; T4N,R3E, Sec. 17; T3N,R2E, Sec. 9; T4N,R3E, Sec. 18; T4N,R4E, Sec. 8; T7N,R3E, Sec. 35;T7N,R5E, Sec. 32; T4N,R1E, Sec. 34 |