Decision Memo Completed

Cable One Aerial Fiber Optic Cable Installation

National Forests in Mississippi Jefferson; Lincoln, Mississippi Homochitto Ranger District

Request to install an aerial fiber optic cable approx. 4,200 feet along an existing aerial powerline network within National Forest land.

Location

Approximately 2.75 miles east of HWY 28 on HWY 550

Project timeline

1
Scoping Start
07/29/2013
2
Comment Period
07/29/2013
3
Decision
10/2013 (Estimated)
4
Implementation
02/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Aerial Fiber Optic Cable (Cable One)Decision Signed Date: 10/31/2013 Legal Notice Date: 11/22/2013
ForestsNational Forests In Mississippi
DistrictsHomochitto Ranger District
Legal Land DescriptionT8N, R5W, sect.17-18
Special use management