Request to bury a telecummunications cable of approximately 500 feet along the MDOT right-of-way along Highway 61, within Forest Service lands.
Location
Approximately 3.25 miles south of the Homochitto River along the MDOT right-of-way of Highway 61.
Project timeline
1
Scoping Start
07/29/2013
2
Comment Period
07/29/2013
3
Decision
02/2014 (Estimated)
4
Implementation
04/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Hwy 61 Buried Telecommunications Cable Installation | Decision Signed Date: 02/20/2014 Legal Notice Date: 03/02/2014 |
| Forests | National Forests In Mississippi |
| Districts | Homochitto Ranger District |
| Legal Land Description | T4N, R2W, sect.37 |