Request to install and operate a saltwater disposal pipeline adjacent to FSR 111a, across approximately 2,500' of National Forest land.
Location
Along FS111a, approximately 2 miles north of Quintin, Mississippi.
Project timeline
1
Scoping Start
06/30/2013
2
Comment Period
06/30/2013
3
Decision
08/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| R.W. Tyson Saltwater Pipeline Request | Decision Signed Date: 08/20/2013 Legal Notice Date: 09/04/2013 |
| Forests | National Forests In Mississippi |
| Districts | Homochitto Ranger District |
| Legal Land Description | T7N, R5E, sect. 31 |