Construction of overhead powerline within existing highway right-of-way.
Location
North side of State Highway 67.
Project timeline
1
Scoping Start
01/09/2014
2
Decision
06/2015 (Estimated)
3
Implementation
08/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Coast EPA - Hwy. 15 Tie-Line | Decision Signed Date: 06/16/2015 |
| Forests | National Forests In Mississippi |
| Districts | De Soto Ranger District |
| Legal Land Description | Sections 13, 14 & 15, T6S, R10W |