Decision Memo Completed

Coast EPA - Hwy. 15 Tie-Line

National Forests in Mississippi Harrison, Mississippi De Soto Ranger District

Construction of overhead powerline within existing highway right-of-way.

Location

North side of State Highway 67.

Project timeline

1
Scoping Start
01/09/2014
2
Decision
06/2015 (Estimated)
3
Implementation
08/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Coast EPA - Hwy. 15 Tie-LineDecision Signed Date: 06/16/2015
ForestsNational Forests In Mississippi
DistrictsDe Soto Ranger District
Legal Land DescriptionSections 13, 14 & 15, T6S, R10W
Special use management