overhead powerline along FDR 912 0.35 miles
Location
Along FDR 912 in pipeline ROW
Project timeline
1
Scoping Start
12/02/2015
2
Decision
05/2016 (Estimated)
3
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Special Use Permit for Utility - Pontotoc EPA Electric Powerline | Decision Signed Date: 05/02/2016 |
| Forests | National Forests In Mississippi |
| Districts | Tombigbee Ranger District |
| Legal Land Description | T12S R4E S5 |