Allowing removal of timber to facilitate road maintenance and stabilization in two locations along Berrytown Road.
Location
Two sites along Berrytown road: one approximately 4/10 mile from the Porter Creek bridge; one approximately 9/10 mile from the bridge.
Project timeline
1
Scoping Start
02/01/2016
2
Decision
06/2016 (Estimated)
3
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Timber Sales (Green) |
| Berrytown Road Maintenance and Stabilization | Decision Signed Date: 06/03/2016 |
| Forests | National Forests In Mississippi |
| Districts | Homochitto Ranger District |
| Legal Land Description | Not Applicable |