The expansion of one gravel pit and development of up to 5 new gravel pits to provide for road reconstruction and maintenance needs of the Forest and local counties.
Location
Union Church Pit, East Woodsman Springs Pit, 110c1 Pit, Applewhite Pit, Bogue Chitto Road Pit, and 154 Pit. See vicinity map for locations.
Project timeline
1
Scoping Start
09/22/2016
2
Comment Period
04/18/2017
3
Objection Period Start
06/28/2017
4
Decision
10/2017 (Estimated)
5
Implementation
10/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Land Use Adjustments; Minerals Or Geology Plans Of Operations; Road Improvements/Construction; Timber Sales (Green) |
| Forests | National Forests In Mississippi |
| Districts | Homochitto Ranger District |
| Legal Land Description | T3N, R2E, Sec 3&4; T3N, R2E, Sec 9; T7N, R3E, Sec 35; T7N, R5E, Sec 32; T6N, R5E, Sec 32; T4N, R1E, Sec 34. |